COST ESTIMATING FORMAT FOR LARGE PROJECTS -
STANDARD OPERATING PROCEDURE
2
Which Large Projects will the CEF be used on?
• The CEF should only be used on large projects for which the permanent restorative work
(Categories C, D, E, F, and G) is less than 50% complete, or will take four or more months to
reach 90% project completion (pre-punch list/contractor retainage stage). CEF should not be
used for large projects that are either greater than 50% complete, or will be 90% complete
within four months (use actual eligible costs). Percent complete is derived from the
approved design and/or construction timeline for eligible work, using the start and
completion dates of the project to determine project duration.
What is the process for preparing an estimate for a Large Project using the CEF?
• Project Officers (POs) are responsible for determining which local factors to use in the
development of the project cost estimate. Specific items are unit price sources, city cost
indices (if applicable), and local costs for plan checks, building permits, or special reviews.
This information will be collected and evaluated at the beginning of each disaster and used
uniformly for all CEF analyses. Prepare the CEF for large project as follows:
• Determine the eligible scope of work and base costs (Part A of the CEF), including Special
Considerations and Section 406 Hazard Mitigation for large projects that meet the criteria
noted in the previous bullet. Part A of the CEF should be completed in accordance with the
guidance provided in the Cost Estimating Format for Large Projects Instructional Guide. All
work activities needed to perform the eligible scope of work will include a written
description of the scope of work, the cost item reference (Construction Specifications
Institute [CSI] based), cost code reference (if FEMA cost codes are used), the unit [linear
foot (LF), square foot (SF), each (EA), cubic yard (CY), etc. - do not use lump-sum (LS)],
the quantity (or measurement), the unit cost and the quantity cost. Each line item's unit
price/subtotal cost will be adjusted to reflect the city cost index where the work will take
place.
• Document the eligible scope of work on the CEF Fact Sheet. Detailed supporting backup
documentation such as site maps (or location plan), photographs, sketches, calculations,
measurements, insurance declarations page, anticipated or actual insurance settlement,
Section 406 HMP proposal(s), construction permits and clearances, force account (F/A)
summary sheets, codes and standards identified in the CEF Notes sheet; and for major
construction activities such as water control facilities and large buildings, to include
schematic drawings; a set of plans preferably reduced to 11" x 17" containing basic
information such as elevations, floor plans, site plan, structural plans and sections, etc., as
applicable, are required from the applicant during the large project formulation process.
Source documents such as invoices, vouchers, timesheets, purchase orders, item slips, weight
slips, plans and specifications, insurance policy, etc. reside with the applicant.
• After the eligible scope of work and its base costs are completed in Part A, the PO will
complete Parts B through H (the factors applied to the base cost) of the CEF. Separate
summaries will be developed for completed and uncompleted work. Assumptions used in
defining factors B through H will be documented in the CEF Notes Sheet.