7
2021
plans and specifications (Cent. Ohio JVS v. Peterson Constr. Co., 129 Ohio App.3d 58, 716 N.E.2d
1210 (12th Dist.1998)), and coordinate separate contractors on multi-prime jobs (Norment Sec.
Group, Inc. v. Ohio Dept. of Rehab. & Correction, Ct. of Cl. No. 2001-11472, 2003-Ohio-6572, 2003
WL 22890088).
Implied duties may also exist between a general contractor to a subcontractor. For example, in
the absence of contract language to the contrary, a general contractor impliedly promises to
provide its subcontractor with reasonable access to the project site, make reasonable efforts to
coordinate the subcontractor’s work, and not interfere or hinder the subcontractor’s
performance.
One of the perennial problems are delays associated with securing necessary government
approvals or permits. This is a bigger problem in fast track projects or those where the design
work is proceeding simultaneously with construction. If there is a problem with the drawings, a
code compliance issue, or other concern by the entity performing the plan review, it can delay
progress until the issue is resolved. In Carrabine Construction Co. v. Chrysler Realty Corp., 25 Ohio
St.3d 222 (1986), the court found that the delays associated with the failure to obtain zoning
approvals were the contractor’s responsibility because of how the obligations were allocated in
the contract. The same principle holds true universally – if there is a delay associated with a
design problem, or in obtaining government approvals, the entity who took responsibility for
those tasks under the contract will face liability for any and all costs associated with the failure
to fulfill that obligation.
B. Breach of Express Warranty
Like many states, Ohio has adopted what is known as the Spearin Doctrine, which holds that
“when a contractor follows an owner's plans, the owner impliedly warrants that the plans are
accurate. If the construction is revealed to be defective [because the plans are inaccurate], the
owner is the responsible party.” Cent. Ohio JVS, at 64, citing United States v. Spearin, 248 U.S.
132, 136 (1918).
Under the Spearin doctrine, it is generally accepted that a public owner warrants the accuracy,
completeness, and suitability of the project plans and specifications. See Central Ohio JVS. An
owner is required to furnish sufficient plans, specifications, and building site for the contractor
to evaluate, price and bid the project and perform the work. If the owner provides the contractor
with materials and equipment or specifies proprietary products for use on the project, then the
owner impliedly warrants the suitability of the equipment or materials. See, Jurgens Real Estate
Co. v. Eastgate Development Partnership, 103 Ohio App.3d 292 (12th Dist.1995); Floor Craft Floor
Coverings, Inc. v. Parma Community General Hospital, 8th Dist. Case No. 56145 1989 WL 24948
(Mar. 16, 1989), aff’d, 54 Ohio St.3d 1 (1990); Lathrop v. City of Toledo, 5 Ohio St.2d 165 (1966).
The Ohio Supreme Court, however, has recently limited the scope of the Spearin Doctrine in Ohio.
In Dugan & Meyers Constr. Co., Inc. v. Ohio Dept. of Adm. Servs., 113 Ohio St.3d 226, 2007-Ohio-
1687, 864 N.E.2d 68, the court held that, under Ohio law, the Spearin doctrine only applies in
those cases where damages flow from the owners “affirmative indications of job site conditions”